Raw Grinding Dust Collector

Duct tie-ins and equipment installation during a three-week plant shutdown.

Raw Grinding Dust Collector — Duct Lifting (1/11)
Raw Grinding Dust Collector — Duct Lifting (1/11)

Project Scope And Execution

Project included approximately five weeks of mobilization and pre-shutdown preparation, followed by critical duct tie-ins and installation of new equipment during a three-week plant shutdown. More than 25,000 lb of structural steel was erected and installed, along with more than 4,000 ft² of insulation on equipment and ductwork.

In total, the project required more than 7,300 labor hours across multiple construction disciplines. Major lifting activities were completed using 250-ton and 175-ton cranes, and extensive chute and ductwork erection was carried out through four levels of the Raw Mill Building, from the upper floors down to the lower process areas.

Discuss Your Plant Or Equipment Challenge

Describe the equipment, operating concern, and improvement you want to evaluate.

Contact Turnell Corp