Synthetic gypsum system 2

Synthetic gypsum handling and feeding for three cement mill systems.

Overall gypsum handling model
Overall gypsum handling model

The project objective was to reduce cement production costs by replacing higher-cost natural gypsum with lower-cost synthetic gypsum from flue gas desulfurization (FGD).

The plant operates three cement mill systems. The installed system includes three dump hoppers, each equipped with four screw feeders. Each hopper discharges onto a belt conveyor equipped with a weigh idler. Each belt conveyor feeds a tubular drag chain conveyor that conveys the gypsum to one of the cement mill systems.